CHINAREVSKOYE OIL & GAS CONDENSATE FIELD PROJECT


SITE: KAZAKHSTAN

Chinarevskoye Field, approximately 324 square kilometres in size, is situated close to the city of Uralsk in West Kazakhstan and is only 60 km from the border with the Russian Federation. The field consists in an oil processing facility capable of processing 400,000 tpa of crude oil, multiple oil gathering and transportation lines, a gas powered electricity generation system, major warehouse facilities for the storage of oil, materials, machinery and chemicals used in crude oil production, an employee field camp for 180 people as well as 14 existing wells and 4 exploration wells under drilling and test operations.

EPC contractor
Exterran/Belleli Energy


End User
ZhaiknMunai LLP


SOLUTIONS DELIVERED
Skema supply included the design, manufacturing, testing and supply of:
• 6 kV MV switchboards (31 sections)
• Intelligent Power Motor Control Centers, including:
- 55 Intelligent Motor Control Centers (240 drawers)
- 20 Power Centers
• Capacitors panels

Delivery time: 18 weeks


ima_1
ima_2 ima_3 ima_4 ima_5